The City of Joliet requires a permit for the demolition of
any building or structure within the City. In order to obtain
a demolition permit from the Inspectional Services Division,
the demolition contractor must follow these steps:
1. Applicant checks requirments for demolition
permit with Building Inspector, including requirements for
fences, barricades, sidewalk sheds, and aprons, and picks
up application.
2. Applicant checks with Director of Public
Works and Utilities Department regarding disconnection of
building from City sewer and water lines. The applicant is
required to disconnect the building from City water and sewer
lines. This disconnection includes removing the water service
line back to the main and plugging the sanitary sewer lateral
at the property line.
3. Applicant notifies utility companies of
the proposed demolition and arranges for disconnection of
all service lines.
4. Applicant secures bond and Certificate
of Insurance (naming City of Joliet additionally insured)
in required amounts.
5. Applicant submits completed application,
bond, or Certificate of Insurance to Building Inspector, with
required fees.
6. If permit is approved, applicant
provides all required protections and proceeds with demolition
under the time schedule shown on the application.
|